University of Limerick, Sports Arena Enabling Works

Project Description

Client

Plassey Campus Developments Ltd.

Project Duration

12 weeks

Design Team

Project Architects
Aecom
Brady Shipman Martin
Malachy Walsh
Willis Risk Management

Project Description

The enabling works included the following:

  • Providing a new temporary access route through adjacent lands to Kilmurry Village
  • Diversion of all existing services including the floodlighting for the all-weather pitch
  • Road re-alignment works this will include building up the bank to support the new roadway and sub base for the road
  • The construction of a new timber crib wall and the construction of the new road way and footpath
  • Construction of new concrete steps
  • Erection of the UL specified permanent hoarding around the entire site for the main contract
  • Landscaping works and making good all external adjacent finishes